The group is at present working with the following set of milestones. These would be adjusted based on work completed and any blockers
Task Item | Due By | Status |
---|---|---|
Outline of the Master Document for v2 with major sections outlined in Table of Contents | 16-Jul-2020 | Completed |
List of all appendices to be included with Master Document for v2 | 16-Jul-2020 | Completed; first pass |
Completion (sign-off and availability) of first draft of main body Master Document for v2 | 16-Aug-2020 | |
Completion (sign-off and inclusion) of first drafts of all appendices of the Master Document for v2 | 30-Aug-2020 | |
General Availability of CCI GF v2 in English | 15-Sep-2020 |
Key milestones will include, but are not limited to:
...
The work of the CCI GF TF will be complete when the participants are ready to instantiate an XXX governance authority to implement the XXX GF.
Meeting Schedule
The Task Force hosts 2 sets of meetings. Meeting notes and agenda are maintained on this document.
- Weekly meetings on Monday at
...
- 4:00pm Paris/Berlin/Cape Town; 10:00am New York; 7:00am San Francisco.
...
- Weekly meetings on Thursday at 1300 (Seoul) ; 0930 (India)